Project: Construction of ENGIE Photovoltaic Power Plant (450 kWp) in Senica
The main aim: Appropriately supplement the local distribution system of ENGIE in Senica with its own electricity production, and thereby increase the share of the use of renewable energy sources in the ENGIE Group in Slovakia
Preparation of project documentation: April – July 2022
Start of construction: July 2022
Completion of construction: December 2022
Start of operation: January 2023
Ground:
Roof: